Akoya Biosciences
When Akoya began to move their Office and Lab infrastructure to their new Marlborough location, DCM was solicited to price a simple Phase 1 scope of work that included (2) new Manufacturing Rooms and (1) QC Lab. After being awarded the Phase 1 scope of work, Akoya added several other scopes of work to the project, including a new fume hood with specialty exhaust fan, and creation of a large cold / freezer room.
DCM completed the work on time and budget to the satisfaction of everyone at Akoya. This goodwill parlayed Phase 1 and Add-On scope into a Phase 2 that included (2) more Manufacturing Rooms, Wet Lab, Electronics Lab, and R&D Lab, plus a Tech Support office.
PROJECT STATS - PHASE 1
- General Contracting
- Design – Ikhan / CMTA Engineers / RG Vanderweil Engineers
- $1,045,000
- 14 weeks
- DCM self-performed demo and rough carpentry
PROJECT STATS - PHASE 2
- Construction Management
- Design – J. Ferrera Associates / Cummings Engineering
- $619,000
- 10 weeks
- DCM self-performed demo, drywall, door install, and carpentry